Allington Data Centre

In December 2015, the Client appointed Omnia Projects to undertake Front End Engineering Design (FEED) for a new 11kV private wire supply from Allington Energy from Waste (EfW) power plant to a new data centre (Maidstone Data Centre).

The project was split into 4 stages:

  • Stage 1 - Enabling works which involved the extension of the existing Allington EfW power plant 11kV switchboard
  • Stage 2 – Provision of an 11kV private wire connection comprising of two 11kV / 3 phase cable feeder circuits
  • Stage 3 – Provision of a new 33kV DNO supply, a new 33kV/11kV substation and two 11kV / 3phase feeder circuits (additional to Stage 2) to Maidstone data centre
  • Stage 4 – Provision of an 11kV interconnector circuit between the 33/11kV substation (Stage 3) and the Allington EfW power plant 11kV switchboard

image.png

Stage 1 and 2 were required to provide the data centre with two 11kV feeds each having a power rating of 25mW the load rating of the DC being 21MW. Stage 3 and 4 were to provide additional resilience to the DC supply.

As part of the FEED, Omnia Projects produced:

  • Site survey reports
  • Cable option reports
  • Cost estimate
  • Basis for design document
  • Stage by Stage drawings

In addition, we also provided technical support to the Clients team on any technical issues that they had regarding the system connection process.

For more information on this project please contact .